York
8,820 delay minutes
The biggest share (18%) of the delay picked up at York in the four weeks to 9 December 2023 came from traincrew problems.
67% of these minutes were knock-on from something that happened elsewhere first. 88% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 531 | 6% | 8% | 19 a day, more than 2 of the other 4 years | 5 |
| Signals, points and power | 818 | 9% | 16% | 29 a day, more than 2 of the other 4 years | 11 |
| Weather and structures | 936 | 11% | 7% | 33 a day, the most in 5 years | 20 |
| Autumn | 494 | 6% | 7% | 18 a day, the most in 5 years | 1 |
| External | 292 | 3% | 4% | 10 a day, more than 3 of the other 4 years | 5 |
| Network management | 1,468 | 17% | 17% | 52 a day, the most in 5 years | 105 |
| The operators' causes | |||||
| Train faults | 1,480 | 17% | 16% | 53 a day, more than 2 of the other 4 years | 40 |
| Traincrew | 1,554 | 18% | 11% | 55 a day, more than 3 of the other 4 years | 130 |
| Stations | 383 | 4% | 3% | 14 a day, the most in 5 years | - |
| Operations | 455 | 5% | 5% | 16 a day, the most in 5 years | 3 |
| Operator, other | 410 | 5% | 7% | 15 a day, more than 2 of the other 4 years | 2 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 901 |
| OU | Delays not Investigated by Network Rail | 650 |
| TH | (Senior) Conductor/Train Manager | 590 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 547 |
| I1 | Overhead line/third rail defect | 324 |
| MD | Technical failures below the solebar | 313 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 279 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 267 |
| MU | Depot operating problem | 213 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 207 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 35,309 |
| TH | (Senior) Conductor/Train Manager | 14,707 |
| MD | Technical failures below the solebar | 14,238 |
| M8 | Technical failures above the Solebar | 12,102 |
| IB | Points failure (including no fault found) | 9,785 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 9,766 |
| MU | Depot operating problem | 9,237 |
| M7 | Door and Door system faults | 8,143 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 7,704 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 7,292 |